Using 5/4x6 wood baseboard trim, with a base cap and shoe in bathrooms with a tiled floor. New work. 3/4" Advantec subfloor. Tile is 3/8" thick and will get 1/2" Durock under it.
Question? What's the best order to have everything installed, and why?
And for purposes of locating the toilet supply during rough-in so that it will end up in the center of the visible part of the baseboard, how high off the sub-floor should it go?
Sorry if these are basic questions.
Thanks,
Tom
Question? What's the best order to have everything installed, and why?
And for purposes of locating the toilet supply during rough-in so that it will end up in the center of the visible part of the baseboard, how high off the sub-floor should it go?
Sorry if these are basic questions.
Thanks,
Tom